The Eva Creek Wind Project is a 24 MW (megawatt) wind farm near Healy AK, operated by Golden Valley Electric Association (GVEA). Construction began in May 2012, with the first power arriving in October 2012.
Golden Valley Electric Association (GVEA) began studying wind potential in the Healy area in 2003 by installing wind-monitoring towers. In 2009 the company further expanded its explorations. Environmental surveys and development plans were initiated in 2010. In 2011, the GVEA board of directors approved the project for construction.
The farm will ultimately contain 12 wind turbines, a substation, an operations and maintenance building, two communication towers and a meteorological tower. The site is located north northeast of Healy, in the valley south of Rex Dome.
GVEA projects that the construction costs for Eva Creek will be around $90 million. Maintenance costs are projected at $1.5 million annually, with another $6 million per year required to service the loan at 2.1% interest. This $7.5 million per year cost translates into 9.8 cents/kWh, which is comparable to the selling price of the power to be produced by the Fire Island Wind project near Anchorage (9.7 cents/kWh).
These estimates, however, have provoked controversy, especially in relation to a competing project, the Delta Wind Farm near Delta Junction. GVEA considered purchasing power from the privately owned Delta Wind Farm but ultimately decided to move forward with their 100% owned Eva Creek project. Proponents of the Delta Wind Farm have argued that Eva Creek will end up costing much more than GVEA currently estimates. A summary of the objections and a response from GVEA can be found here.
By David Coil, Niki Hoagland, Bretwood Higman, Ground Truth Trekking
Content on this page is available under a Creative Commons Attribution Non-Commercial license. For commercial uses please contact us.
Date Created: 19th December 2011
Chikuminuk Lake Hydroelectric Project (05/06/2013)
Can Two Wrongs Make a Right? Mercury and Selenium in Fish (05/05/2013)
The Eva Creek Wind Farm began producing power in October 2012.
Twitter Updates:@GroundTruthTrek:I always appreciate it when media makes us seem normal.... http://t.co/6uWaxlURyc
@GroundTruthTrek:Catch us at 10AM tomorrow morning on Talk of Alaska on Alaska Public Radio! (and call in with any questions or thoughts).
@GroundTruthTrek:Lituya on the muddy rocks of Turnagain Arm. http://t.co/6E5vwQqGsT
@GroundTruthTrek:From Kenai to Anchorage, by mud and tides... Check out the latest post on our journey.... http://t.co/iHRvSnyRMH
@GroundTruthTrek:Along with new survey results showing 97% consensus in scientific papers that climate change is manmade and... http://t.co/FpV8XQEfY9